Project Update: Harmon Cove

Tocci Stock

Construction has begun at 45 Meadowlands Parkway. The team reports that site work and foundation will take place simultaneously, in the shared, tight space. Right now, drainage and utilities are being installed alongside foundation crews cutting piles and excavating for grade beams.

Although new drawings are popping up here and there, the team continues to forge ahead, keeping the project on schedule and below budget. We’ll keep you posted!

 